Monday, September 6, 2021

Week 371

 Sun, Sep 5, 2021 thru Sat, Sep 11, 2021

CountPriorityKey
3ATop - This Week
2BTop - Next Week
5CMid - This Month
9DMid - Next Month
4ELow - This Year
3FLow - Next Year
35GCompleted/Done!
61

Project Priority List
PriorityOrigination DateLatest UpdateProject NameProject DescriptionDone! Date
A5/13/20215/13/2021ballast RIP Shopfinishing touches
A8/30/20219/4/2021Finish sidewalks and fences at Industrial ParkExtension for warehouses
A7/1/20217/1/2021Finish wiring Crossover 2.5Will need to figure this out.
B5/11/20215/11/2021West Chicago StationPlatform/lighting
B5/11/20215/11/2021Finish Bridge/UnderpassMelrose Park downtown curbs, sidewalks, gutters, buildings
C5/11/20215/11/2021Winfield/Berkeley StationPlatform/lighting
C5/11/20215/11/2021Oak Park Marion Street StationLighting/kitbashing
C5/18/20215/18/2021Mainline ballastingBetween Crossover #2 and WeGo Diamonds - back tracks in front of WeGo downtown
C6/4/2021Finish decoder installationUP SD50 #53
C8/23/20218/26/2021Finish up details on the Industrial Park ExtensionFinish landscaping and ballasting track

Sun, Sep 5, 2021

Another week of trains...

Setting up the tape for painting the gutters.

Finished painting the sidewalks and gutters.

Tape removed and ready to reinstall the buildings.

Buildings reinstalled and ready for more details.

Close up of the wrap around sidewalk.
Hardly anyone will see this part since it's on the backside of the building away from viewing.

Same thing with this sidewalk on the other warehouse building.
No one will notice the sidewalk isn't large enough for the stupe.

Mon, Sep 6, 2021

Adding a bit of detail to the Industrial Park...

Parked cars, trailers at the dock are just a couple of details added.

I like the distant in the dark.
Really makes the bill board stand out.

Employee parking.
Looks like everyone made it to work today.
There's even a FedEx delivery van Ready to GO!


Yes, the FedEx delivery van is to proper scale. The others are a bit too big.

After visiting the Crockett family in Chicago, I did one little project on the RR

I'm working on the details around the warehouse buildings on the Industrial Park extension.
I painted the base of the mulch bed before I add the mulch and plant some bushes for landscaping.

Tue, Sep 7, 2021

Pouring the glue in place. Getting ready to spread the mulch.

Mulch all spread out and now we're ready for planting the bushes.

And there you have it.
All in a days work.

Wed, Sep 8, 2021

Mainly cleaned up the rr room getting ready for tomorrow's Train Day!

Powder River Basin round table.

Central Control Tower round table.

Proviso Yard round table.

All set for Train Day tomorrow.

Thu, Sep 9, 2021

Train Day!
Moved from Monday to Thursday due to Labor Day Holiday.
w/Rob Fair, Jordan Osborn and special guest, Milt Feryance
6-8pm 2 hrs.

And here's our players for tonight's activities...
Rob Fair will be working on the parking lot lines and weathering.

Jordan Osborn will supervise the operations from his perch at the Central Control Tower.

SPECIAL GUEST
Milt Feryance will be our engineer for tonight's trains.
The Steam Excursion and a mixed freight, Train 5C.

Milt begins the evening with the steam excursion train. Here he is preparing to connect to the end of the train, pull it out, and then do a run-around to the front of the train.

Rob's progress on the parking lot lines...

...and weathering.

We thought the lines were a bit too long, so Rob is trimming them down.

As Milt continues lap 2 with the Excursion Train.


Our Special Guest takes the throttle of the Excursion Train
Length: 00:00:25 sec.

End of the line. Putting away the Steam Excursion...
Length: 00:00:22 sec.

Rob Fair checking out the mixed freight heading west at Geneva station.

The last 20 minutes we ran Train 5C a mixed freight
with the AC6000
Length: 00:00:30 sec.

Fri, Sep 10, 2021

No train activity today.

Sat, Sep 11, 2021

Just some cleanup from operations on Thursday.

On Thursday we left Train B515C5D on the main line.
Today, I ran another lap and put the train in Proviso Yard UP.

The last part of the train stayed on the incoming Track 1 show by the arrow.

The first part of the train was backed up into Track 2 as shown by the other arrow.

Now it's time for paperwork.
I'll take these papers upstairs and enter them into the computer.

Here we are upstairs at the computer doing my data entry.

And later today I had a very special guest...

Ida Zielke helping me at the workbench
Length: 00:00:25 sec.

More of Ida helping me power up the steam engine
Length: 00:00:21 sec.

I showed Ida what I have been working on...
She was interested and started playing with the cars on location.

Engineer Ida looks far off to Elmhurst to see her train waiting on Elmhurst station.

Finally we reach our destination - Geneva Station.
We left Chicago Terminal 23 minutes prior and made every stop except Kedzie Avenue.

Ida didn't have enough energy for the return trip to Chicago so 
I'll need to capture another crew for that assignment.

CountPriorityKey
0ATop - This Week
0BTop - Next Week
2CMid - This Month
15DMid - Next Month
4ELow - This Year
3FLow - Next Year
37GCompleted/Done!
61

Project Priority List
PriorityOrigination DateLatest UpdateProject NameProject DescriptionDone! Date
E5/13/20215/13/2021ballast RIP Shopfinishing touches
G8/30/20219/4/2021Finish sidewalks, fences, parking lanes, weatheringIndustrial Park Extension for both warehouses9/9/2021
C7/1/20217/1/2021Finish wiring Crossover 2.5Will need to figure this out.
C5/11/20215/11/2021West Chicago StationPlatform/lighting
D5/11/20215/11/2021Finish Bridge/UnderpassMelrose Park downtown curbs, sidewalks, gutters, buildings
D5/11/20215/11/2021Winfield/Berkeley StationPlatform/lighting
D5/11/20215/11/2021Oak Park Marion Street StationLighting/kitbashing
D5/18/20215/18/2021Mainline ballastingBetween Crossover #2 and WeGo Diamonds - back tracks in front of WeGo downtown
D6/4/2021Finish decoder installationUP SD50 #53
D8/23/20218/26/2021Finish up details on the Industrial Park ExtensionFinish landscaping and ballasting track
D6/5/20216/5/2021Working on LocomotivesCNW SD40-2 #6928, UP SD50 #53, RTA F40PH #138Finishing one by one
D5/11/20215/11/2021Oak Park Marion Street DowntownStreets, sidewalks, gutters
D5/11/20215/11/2021Redo Digitrax Sound DecoderGP50 #53 w/Carlos
D5/11/20215/11/2021Install Sound DecoderF40PH #138 w/Carlos
D5/11/20215/11/2021Building under constructionChicago Downtown - cross beams, flooring, lights, facade
D5/13/20215/13/2021Ballast mainline through WeGoPaint ballast first
D5/29/2021Finish writing procedures3Rolling Stock Train Assignments
D6/29/20216/29/2021Wire up the lights for the cars on the PRB overpassWill need to purchase the cars first
D7/15/20217/15/2021Adding cars with lights on PRB overpassNeed to redrill holes and purchase cars to complete project

I've had to readjust these projects to a more realistic outcome.
I've made some of them later in the month or even later this year.
I need to work on my short term goals better.

3 comments: