Sun, Jun 20, 2021 thru Sat, Jun 26, 2021
Count | Priority | Key |
2 | A | Top - This Week |
4 | B | Top - Next Week |
5 | C | Mid - This Month |
9 | D | Mid - Next Month |
4 | E | Low - This Year |
3 | F | Low - Next Year |
8 | G | Completed/Done! |
35 | |
Project Priority List |
Priority | Origination Date | Latest Update | Project Name | Project Description | Done! Date |
A | 6/5/2021 | | Working on Locomotives | CNW SD40-2 #6928, UP SD50 #53, RTA F40PH #138 | Finishing one by one |
A | 5/11/2021 | 5/16/2021 | PRB Overpass | Prepare for illuminated truck headlights | Started first section |
A | 5/18/2021 | 5/18/2021 | Purchase one more early overpass kit | Need one more section to complete this project | Need to get to B&G |
B | 5/17/2021 | 5/17/2021 | Wire up the lights for the trucks on the PRB overpass | Will need to purchase another packet of early bridge works by Rix | |
B | 5/11/2021 | 5/11/2021 | West Chicago Station | Platform/lighting | |
B | 5/11/2021 | 5/11/2021 | Finish Bridge/Underpass | Melrose Park downtown curbs, sidewalks, gutters, buildings | |
B | 5/13/2021 | 5/13/2021 | RIP Shop track floor inside building | do this before ballasting |
Sun, Jun 20, 2021
Happy Father's Day
Mom & Dad stopped by to get a layout update.
|
Mom & Dad stopping by for a layout update. |
I will show you the layout update tomorrow during Train Day!
Mon, Jun 21, 2021
Train Day!
w/Rob Fair & Jordan Osborn
6-8pm 2 hrs.
ALSO!
My monthly video update filmed tonight...
June Layout Update YouTube Video
Length: 00:04:35 min.
|
Rob Fair working on the GP50 #53 trying to get it to run smoothly and with lights. |
|
It's a very tedious job to get all those wires tucked in and out of the way. |
|
We also worked on the CNW SD40-2 #6928. We got it to run with minimal sound interference. |
Tue, Jun 22, 2021
I've been working really hard to get the operation spreadsheets up and running...
|
This worksheet shows the beginning steps of switching the commuter coaches/cabs from Chicago Terminal (CT) to the California Avenue Maintenance Facility (CAMF). |
|
Here are my notes of the movements that need to be made to make it happen. |
|
On the layout this is where the action will take place. This is Chicago Terminal (CT) and then the next picture is... |
|
This is California Avenue Maintenance Facility (CAMF) where the coaches/cabs will be maintained. |
|
For me to write down the switches that need to be thrown, I needed this track map. |
|
This worksheet is the final product. Each step written out and well documented for the conductor and engineer to follow as they go about completing their mission. |
Wed, Jun 23, 2021
|
Banner night! I have completed the task of updating all the Train Codes w/corresponding Power Assignments. Each section is updated. I have a few more worksheets to complete before all the sheets are DONE! |
Thu, Jun 24, 2021
No train activity.
Fri, Jun 25, 2021
No train activity.
Sat, Jun 26, 2021
Trip to B&G today...
|
I spent an additional $3 after the $75 generous Father's Day gift from my very thoughtful children! |
|
Here's the breakdown of the items I purchased. |
|
I also returned item #1 $6.95. Mike replaced the Fencing package as equal value for $6.90. |
|
When I got home I started putting the second part of the bridge together. |
|
Here it is fully assembled. |
|
Another perspective. |
Count | Priority | Key |
2 | A | Top - This Week |
4 | B | Top - Next Week |
Project Priority List |
Priority | Origination Date | Latest Update | Project Name | Project Description | Done! Date |
A | 6/5/2021 | 6/5/2021 | Working on Locomotives | CNW SD40-2 #6928, UP SD50 #53, RTA F40PH #138 | Finishing one by one |
A | 5/11/2021 | 5/16/2021 | PRB Overpass | Prepare for illuminated truck headlights | 6/26/2021 |
A | 5/18/2021 | 5/18/2021 | Purchase one more early overpass kit | Need one more section to complete this project | 6/26/2021 |
B | 5/17/2021 | 5/17/2021 | Wire up the lights for the trucks on the PRB overpass | Also added another truck to illuminate at PRB | |
B | 5/11/2021 | 5/11/2021 | West Chicago Station | Platform/lighting | |
B | 5/11/2021 | 5/11/2021 | Finish Bridge/Underpass | Melrose Park downtown curbs, sidewalks, gutters, buildings | |
B | 5/13/2021 | 5/13/2021 | RIP Shop track floor inside building | do this before ballasting |
Wow....so organized. Love all the progress Dad!
ReplyDeleteWow! So organized! Love the the progress, Dad!