CountPriorityKey
2ATop - This Week
4BTop - Next Week
5CMid - This Month
9DMid - Next Month
4ELow - This Year
3FLow - Next Year
8GCompleted/Done!
35

Project Priority List
PriorityOrigination DateLatest UpdateProject NameProject DescriptionDone! Date
A6/5/2021Working on LocomotivesCNW SD40-2 #6928, UP SD50 #53, RTA F40PH #138Finishing one by one
A5/11/20215/16/2021PRB OverpassPrepare for illuminated truck headlightsStarted first section
A5/18/20215/18/2021Purchase one more early overpass kitNeed one more section to complete this projectNeed to get to B&G
B5/17/20215/17/2021Wire up the lights for the trucks on the PRB overpassWill need to purchase another packet of early bridge works by Rix
B5/11/20215/11/2021West Chicago StationPlatform/lighting
B5/11/20215/11/2021Finish Bridge/UnderpassMelrose Park downtown curbs, sidewalks, gutters, buildings
B5/13/20215/13/2021RIP Shop track floor inside buildingdo this before ballasting

Sun, Jun 20, 2021

Happy Father's Day
Mom & Dad stopped by to get a layout update. 
Mom & Dad stopping by for a layout update.

I will show you the layout update tomorrow during Train Day!

Mon, Jun 21, 2021

Train Day!
w/Rob Fair & Jordan Osborn
6-8pm 2 hrs.

ALSO!

My monthly video update filmed tonight...

June Layout Update YouTube Video
Length: 00:04:35 min.

Rob Fair working on the GP50 #53 trying to get it to run smoothly and with lights.

It's a very tedious job to get all those wires tucked in and out of the way.

We also worked on the CNW SD40-2 #6928. We got it to run with minimal sound interference.


Tue, Jun 22, 2021

I've been working really hard to get the operation spreadsheets up and running...

This worksheet shows the beginning steps of switching the commuter coaches/cabs from
Chicago Terminal (CT) to the California Avenue Maintenance Facility (CAMF).

Here are my notes of the movements that need to be made to make it happen.

On the layout this is where the action will take place.
This is Chicago Terminal (CT) and then the next picture is...

This is California Avenue Maintenance Facility (CAMF) where the coaches/cabs will be maintained.

For me to write down the switches that need to be thrown, I needed this track map.

This worksheet is the final product.
Each step written out and well documented for the conductor and engineer
to follow as they go about completing their mission.


Wed, Jun 23, 2021

Banner night!
I have completed the task of updating all the Train Codes w/corresponding Power Assignments.
Each section is updated. I have a few more worksheets to complete before all the sheets are DONE!

Thu, Jun 24, 2021

No train activity.

Fri, Jun 25, 2021

No train activity.

Sat, Jun 26, 2021

Trip to B&G today...

I spent an additional $3 after the $75 generous Father's Day gift from my very thoughtful children!

Here's the breakdown of the items I purchased.

I also returned item #1 $6.95.
Mike replaced the Fencing package as equal value for $6.90. 

When I got home I started putting the second part of the bridge together.

Here it is fully assembled.

Another perspective.


CountPriorityKey
2ATop - This Week
4BTop - Next Week

Project Priority List
PriorityOrigination DateLatest UpdateProject NameProject DescriptionDone! Date
A6/5/20216/5/2021Working on LocomotivesCNW SD40-2 #6928, UP SD50 #53, RTA F40PH #138Finishing one by one
A5/11/20215/16/2021PRB OverpassPrepare for illuminated truck headlights6/26/2021
A5/18/20215/18/2021Purchase one more early overpass kitNeed one more section to complete this project6/26/2021
B5/17/20215/17/2021Wire up the lights for the trucks on the PRB overpassAlso added another truck to illuminate at PRB
B5/11/20215/11/2021West Chicago StationPlatform/lighting
B5/11/20215/11/2021Finish Bridge/UnderpassMelrose Park downtown curbs, sidewalks, gutters, buildings
B5/13/20215/13/2021RIP Shop track floor inside buildingdo this before ballasting