Sun, Nov. 8, 2020 thru Sat, Nov. 14, 2020
This week's goals:
1. Begin work on California Ave. Metra Maintenance Facility entrance off Western Ave.
Progress: Not Started
2. Finish lighting at Melrose Park Power Station
Progress: Working on it.
3. Start work on CNW Power Plant
Progress: Lots of thinking, no action yet
Sun, Nov. 8, 2020
In order to light up the Power Plant we need to do some leg work to get the footprint ready. Step 1: Lay down the "asphalt" base |
Another view... |
And another view... |
Power plant lights installed. First row of parking lot lights installed. |
Checking building placement over lighting. |
Mon, Nov. 9, 2020
Rob Fair checking light fixtures making sure they are working before we install them. |
Rob Fair and Jordan Osborn Jordan stopped by for a cameo appearance. |
Removing the "footprint" in order to begin the lighting. |
The top of the washing machine turned out to be a great place for our work place. |
Rob Fair glues in the light posts to keep them in place while we place the footprint on its side for wiring. |
Hard to see the wires, but they're there. |
Rob Fair preparing the connections. |
We finished wiring up the street lights in parallel circuit. |
Tue, Nov. 10, 2020
The building lights are all connected. Street lights on the left, building lights on the right. |
Then I put electrical tape and thumbtacks to keep the wires in place so they won't get caught when putting the "footprint" back in place. |
Ready to put back in place... |
This afternoon I was able to get the wires
Now we're ready for the structures. |
Structures in place with working lights. |
Better looking in person. I hope to see you soon! |
Finished Goal #2!
Wed, Nov. 11, 2020
After I figured out all the underside wiring, here's how it looks on the top side. Coal train waiting for unloading and lights working inside the power plant and substation. |
Thu, Nov. 12, 2020
Fri, Nov. 13, 2020
Copper tubing, Spade terminals, balsa wood. |
Here's the cost for CNW Power House Project |
I like to work at the dining room table because there's lots of light. Watch as the table fills up with tools and other stuff. |
I found my kitbashing materials. Getting ready to start installing the base...keep watching... |
You'll need to go to Week 329 for the progress on this project.
Sat, Nov. 14, 2020
Progress report on this week's goals:
1. Begin work on California Ave. Metra Maintenance Facility entrance off Western Ave.
Progress: Not Started
2. Finish lighting at Melrose Park Power Station
Progress: DONE! Finished Wed, Nov. 11, 2020
3. Start work on CNW Power Plant
Progress: Officially restarted this week (Fri, Nov. 13, 2020)