Sun, Nov. 29, 2020 thru Sat, Dec. 5,2020
This Week's Goals:
1. Continue work on CNW Powerhouse
Progress: finish painting the back & side outside walls.
2. Install lights on CNW Powerhouse chimney
Progress: Train Day! project - wire them up!
3. Begin work on California Ave. Metra Maintenance Facility entrance off Western Ave.
Progress: Not Started
Sun, Nov. 29, 2020
I want to add an overpass over the PRB lead tracks. So let's see what we have in stock. |
Then I went to the CNW Powerhouse and removed the weights to see what we have. |
While at the Powerhouse I decided to add the trees. Here are the holes I made for the trees with an auger. |
Also felt inspired once at the CNW Powerhouse, I decided to get ready to paint. Here I installed the middle and end pieces. |
Then I did something really dumb. I installed the windows, but later figured out I need to take them out for painting. UGH! |
Here's one of the back walls with the middle and end pieces in place. The parts between the wall sections that keeps them connected. |
Getting ready to paint... |
Mon, Nov. 30, 2020
Tonight Rob Fair is going to wire up the lights for the CNW Powerhouse and then we're going to connect to power and see what happens. |
Jordan Osborn found a new game to play on his new phone. |
Back at the workbench: Rob Fair begins to solder the end of the black wires. |
We also decided to paint the bottoms of the lights black...as well as... |
...the sides. |
Our test was successful! BUT, when we tried again after putting all the shrink wrap in place it failed. One light didn't light, just one! |
I was really bummed, because now we need to start all over and do all the soldering over again. Rob said not to wait until next week. So I'll tackle this one myself and see if we can get that chimney installed with lights this week. That's my goal...to finish Goal #2.
Tue, Dec. 1, 2020
Time to paint. Check out what happens with the foam board underneath the model... |
The spray paint ate away on the foam board and left the wall impression on the surface. |
Now to put the pieces in place and see how it fits. |
I'll need to do some trimming and fitting, but I think this will work. |
Drone view... |
Remember how we were having light issues last night? Well I went back and tried to find the culprit... |
...but I couldn't find it. However, I did crimp the wires a bit and now they work. |
Looks good, don't you think?
Wed, Dec. 2, 2020
Before entertaining our special guests I was able to finish repairs on the chimney lighting. |
And here's ONE of our Special Guests: Charlie Zielke! |
And here's ANOTHER ONE of our Special Guests: Ida Zielke! |
Charlie at the controls - sounding the bells. |
Check out these cute videos of our guests in action...
Thu, Dec. 3, 2020
Chimney lights installed. How does it look? |
The drone view. |
Now it's time to start on the perimeter... |
Putting in the back wall windows. |
How they look in place. |
Starting work on the base of the building. Prototype on the right ---> <---Model on the left. |
Fri, Dec. 4, 2020
Sat, Dec. 5, 2020
Working on the bottom section of the Milwaukee Avenue side. |
Gluing the sections in place. |
Adding the doors at the far left of the facility. |
Finally, painting the base and the door entries. |
Looking at the model and prototype side by side.
Now it's time to work on the final trim pieces. |
All painted and looking good. |
Drone view from the front. |
Drone view from above Lake Street. |
Drone view from the back. |
My paperwork for the interior support walls and the roof panels. |
This Week's Goals Progress Report:
1. Continue work on CNW Powerhouse
Progress: Finished installing the back and side walls. DONE! Sat, 12/5/20
2. Install lights on CNW Powerhouse chimney
Progress: Train Day! project - wire them up! DONE! Tue, 12/1/20
3. Begin work on California Ave. Metra Maintenance Facility entrance off Western Ave.
Progress: Not Started