Sunday, February 22, 2015

Week 32

New Week beginning Sunday, February 15, 2015

Reminder: Most recent at top - Latest on the bottom

Here are the days of action:


Thursday, February 19, 2015
Carlos Baez Started laying Cork Trackbed Lay Mainline Cork Trackbed
Carlos Baez Finished Electical Wiring at CCT DONE! Electrical Wiring - Control Panel!
Curt Berg Special Projects - worked with the guys where needed Special Project
Dean Hatzis Worked on slope transitions at ground zero & corners Draw Track Plan on Pressed Wood
Ed Nelson Finished painting all mainlines , now middle sections Pressed Wood Layout Surface



 Dean Hatzis working on the corner elevation.

 Last time you'll see Carlos at the electrical panel. 
He's completed his task!

 Ed Nelson begins the ascent to the summit painting the mainlines.

 Final preparations for securing the junction box and calling it complete!

 Ed Nelson coming back down from the summit.

 A little out of order, but here, Ed had to do some additional taping before painting.

 After finishing the electrical work on the Central Control Tower, Carlos Baez began work on the cork trackbed. We're getting closer to running trains!  Choo, choo.

 Ed Nelson working on the tape before finishing painting the mainline areas.



 More cork trackbed. Taking shape wouldn't you say?



 After Dean finished the one corner, 
he began working on the elevation challenge. 1/2" to 0.



 Ed Nelson, finished project - mainline area painting.
Next week, the rest!



Sunday, February 15, 2015
Curt Berg Continued pulling tape off painted mainlines Pressed Wood Layout Surface

 Jan took these photos so she has also been added to those who have participated in this grand project!

 Proviso Yard pulling up the tape from East to West
NEAR

 FAR


 Central Control Tower - Track Lights are on. Can you tell?




No comments:

Post a Comment