Tuesday, July 20, 2021

Week 364

 Sun, Jul 18, 2021 thru Sat, Jul24, 2021

CountPriorityKey
2ATop - This Week
3BTop - Next Week
6CMid - This Month
12DMid - Next Month
4ELow - This Year
3FLow - Next Year
19GCompleted/Done!
49

Project Priority List
PriorityOrigination DateLatest UpdateProject NameProject DescriptionDone! Date
A7/10/20217/17/2021Finish installing PRB street lightsWiring up feeders before re-installing
A7/18/20217/18/2021Install UP5 at Geneva StationAllows switching at Global 1
B5/11/20215/11/2021West Chicago StationPlatform/lighting
B5/11/20215/11/2021Finish Bridge/UnderpassMelrose Park downtown curbs, sidewalks, gutters, buildings
B5/13/20215/13/2021RIP Shop track floor inside buildingdo this before ballasting

Sun, Jul 18, 2021

I had to move fast to try to capture my wife, Jan, in this picture. 
As you can see, I wasn't fast enough because the picture is still blurred.
Dang!
Sure wish it was clear. It would've been a great shot of Jan and my son, Ben!

On the other hand, this one turned out just great!
I was surprised I got such a nice smile from my grandson, Josiah.
He usually avoids the camera. 
Also in the picture is my granddaughter, Lissette, and my daughter, Natalie.

Mon, Jul 19, 2021

No train activity today.

Tue, Jul 20, 2021

No train activity today.

Wed, Jul 21, 2021

I forgot to take a picture of my birthday present given by my dear children!

Thank you very much to Emily & Brian, Ben, James & Natalie!

You are the best kids ever!!!

This is what I bought from the gift given by my children for my birthday back in April.
1. Loconet cables to connect to #3 (Item $17.00 S&H $6.99 Tax $1.36)
Gift card amt.: $12.29 My cost: $13.06
2. LED 12v lights for lamps (Item $10.99 S&H $5.99 Tax $.88)
Gift card amt.:  $17.86
3. UP5 Digitrax Loconet face plate and module (Item $18.38 Tax $1.47)
Gift card amt.: $19.85
Totals: Gift card amount: $12.29 + $17.86 + $19.85 = $50
My cost over and above gift card amount: $13.06

I had to change the location for the UP5 since the cable wouldn't reach the previous location.

Spot of previous location.

Newly installed UP5.
The station covers the old location in the distance.

Thu, Jul 22, 2021

No train activity today.

Fri, Jul 23, 2021

I finally wired up the Coal Plant parking lot lights.
Maybe a bit too bright, but we'll go with the look for now.

I wanted to take a picture from a distance to see what it looks like.

SPECIAL GUEST
This is Tyler Wierzbinski.
He works for Fresh Air dryer duct cleaners.
When he came downstairs the first thing he said was, "Wow!"
He made my day!

In order to prepare the street lights for installation I added the resistor and feeder wires.

Here's the technique I used to solder the ends.

SPECIAL GUESTS
Emily and Ida Zielke stopped by this evening and checked out the trains.
Charlie also was here but didn't want his picture taken.

Sat, Jul 24, 2021

Lots of work done on the RR today...take a look:

Working under the layout to wire up the lights. Very tedious work.

Here's what it looks like under the table.

Finished the street lights at the Powder River Basin
Length: 00:00:25 sec.

Looking down the end of the street at Harvard or beyond the Powder River Basin.

Drone view of the intersection and the Coal Plant in the distance.

Close up of the road crossing over the tracks.

Ida's first reaction to the street lights.
Charlie wants to know about the motorcycle...
Length: 00:00:31 sec.

My two train fans. They did a great job today!

Charlie is the engineer. Ida is the conductor.
Length: 00:00:30 sec.

After one lap, still watching the train...
Length: 00:00:26 sec.

This was Charlie's train where he was the engineer and Ida was the conductor.

This is the Train Order Sheet that will capture the moment.

After Ida and Charlie left I put together this intermodal train.

This is the Train Order Sheet that will capture the moment historically.

A drone's view of the intermodal train waiting to proceed on the mainline.


CountPriorityKey
0ATop - This Week
3BTop - Next Week
6CMid - This Month
12DMid - Next Month
4ELow - This Year
3FLow - Next Year
21GCompleted/Done!
49

Project Priority List
PriorityOrigination DateLatest UpdateProject NameProject DescriptionDone! Date
G7/10/20217/17/2021Finish installing PRB street lightsWiring up feeders before re-installing7/24/2021
G7/18/20217/18/2021Install UP5 at Geneva StationAllows switching at Global 17/21/2021
B5/11/20215/11/2021West Chicago StationPlatform/lighting
B5/11/20215/11/2021Finish Bridge/UnderpassMelrose Park downtown curbs, sidewalks, gutters, buildings
B5/13/20215/13/2021RIP Shop track floor inside buildingdo this before ballasting




1 comment:

  1. Powder River is looking great ! ! ! You are making amazing progress ! ! !

    ReplyDelete